How to Calculate Profit on AV Installation Jobs

Compare the quote with what the project actually cost.

Start with project revenue

Add the contract amount and approved changes. Keep sales tax collected on behalf of a tax authority out of project revenue. For example, a $12,000 contract and a $1,000 approved change give you $13,000 in project revenue.

Total the direct costs

Suppose equipment costs $6,000, technicians record 40 approved hours at a $55 loaded hourly cost, and other direct expenses total $400. Direct cost is $8,600. Use your internal loaded labor cost for this calculation.

Calculate gross profit and margin

Subtract $8,600 from $13,000 for $4,400 in gross profit. Divide $4,400 by $13,000 for a 33.8% gross margin. Compare each cost category with the estimate to see what changed. This job-level figure comes before company overhead and income taxes.